Guyana seeks another US$118M for delayed Gas-to-Energy project

Sharing is caring!

The government is back in Parliament asking for more money for the Gas-to-Energy project — another GY$24.7 billion (US$118.4 million) — to get the delayed 300-megawatt plant at Wales into operation in 2027.

  • Finance Minister Dr. Ashni Singh presented the request to the National Assembly on Nov 18, as part of GY$89.8 billion in supplementary financial papers.
  • With this request, 2026 provisions for the project total about GY$54.49 billion (US$261.4 million) — GY$10.72 billion originally budgeted, plus GY$19.09 billion previously sought.
  • Parliament has not approved it yet.
  • Separately, the US EXIM Bank extended the deadline to draw on the project’s loan to Dec 30, 2027. Guyana had asked for Sep 30, 2027. The loan amount does not change.
  • The plant was supposed to be finished in 2024. First turbine commissioning is now expected by yearend.

The Gas-to-Energy project was supposed to be done in 2024. It is now 2027 on the calendar, and the government is back asking Parliament for more money.

Finance Minister Dr. Ashni Singh laid the request before the National Assembly on November 18 — another GY$24.7 billion (US$118.4 million) for the project, tucked inside GY$89.8 billion of supplementary financial papers covering everything from roads to the airport.

The bill keeps growing. The project started 2026 with GY$10.72 billion budgeted. Another GY$19.09 billion was sought earlier. Add this latest request and the 2026 total hits about GY$54.49 billion (US$261.4 million). And none of this latest chunk is approved yet — Parliament still has to say yes.

There is a bit of breathing room on the financing side. The US EXIM Bank has pushed the deadline to draw on the project’s existing loan from September 1, 2026 to December 30, 2027. Guyana had asked for September 30, 2027 and got three months more than that. The loan itself does not get bigger, and the construction schedule does not change.

When it finally runs, the 300-megawatt plant and natural gas liquids facility at Wales, West Bank Demerara, will burn gas piped in from ExxonMobil’s Stabroek Block. The government says it will make electricity more reliable and much cheaper to generate — and that is supposed to mean lower rates for consumers. Power demand could rise fivefold by 2030, so the pressure to finish is only going up. The first turbine is expected to start up by yearend.