ExxonMobil moves Longtail to execution — Saipem gets $1–1.5B subsea go-ahead, SBM wins FPSO job
ExxonMobil has moved its Longtail gas project from approval into execution, handing out the two biggest pieces of work on the same day. Saipem has been given the go-ahead on the $1–1.5 billion subsea package, and SBM Offshore has won the contract to build and install the floating production vessel and run it for 10 years. It is the latest step for the $12.5 billion project — Guyana’s eighth offshore development and its first built on gas rather than oil — which was approved on November 12 and is targeted to start up in 2030.
The key points:
- Saipem authorised to proceed with the remaining subsea work — engineering, procurement, construction and installation of the subsea structures, umbilicals, risers and flowlines (SURF) — worth an estimated $1–1.5 billion overall, with about four years of work ahead.
- SBM Offshore won the FPSO contracts — build and install the vessel, then operate it for an initial 10 years. No contract value was disclosed.
- The FPSO will be SBM’s sixth for ExxonMobil Guyana, built on its Fast4Ward design, with the highest gas-handling capacity ever put on an FPSO: 1.2 billion cubic feet of gas a day and 250,000 barrels of condensate, storing about 2 million barrels, in about 1,750 metres of water.
- Saipem’s Guyana-side logistics will run from the Vreed-en-Hoop Shorebase, with equipment fabricated in Sardinia, Italy. SBM says it intends to source some fabrication locally but has not named any Guyanese firms.
- The $1–1.5 billion is the whole subsea package — not extra spending on top of the $12.5 billion project cost. It follows a roughly $150 million limited notice to proceed in April 2026.
- Longtail is the eighth Stabroek development and the first built on non-associated gas and condensate: about 45 wells across nine reservoirs, with start-up targeted for 2030. Partners are ExxonMobil with 45%, Hess with 30% and CNOOC with 25%.
Full story:
ExxonMobil Guyana has moved its Longtail development into execution, authorising Saipem to proceed with the subsea work and awarding SBM Offshore the contract for the floating production vessel, both announced on Monday, November 17.
Saipem said it had received authorisation from ExxonMobil to proceed with the remaining execution activities under its engineering, procurement, construction and installation (EPCI) contract for the project’s subsea structures, umbilicals, risers and flowlines system. The contract has an estimated overall value of between $1 billion and $1.5 billion, with execution expected to take around four years.
The work follows a limited notice to proceed of about $150 million that Saipem received on April 21, 2026, which allowed preliminary detailed engineering and procurement of long-lead equipment to begin while the main construction and installation scope awaited the final investment decision.
Saipem will carry out offshore operations using vessels from its fleet, including the FDS2, Castorone and Constellation. Equipment will be fabricated in Sardinia, Italy, and Guyana-side logistics will be managed from the Vreed-en-Hoop Shorebase.
It is Saipem’s eighth offshore development contract from ExxonMobil Guyana, following Liza Phase 1 and Phase 2, Payara, Yellowtail, Uaru, Whiptail and Hammerhead.
Separately, SBM Offshore said it had won contracts to construct and install the FPSO for the Longtail development and expects to operate the vessel for an initial period of 10 years. The company did not disclose the value of its award.
The award follows the completion of front-end engineering and design studies and the final investment decision on the project. The FPSO design is based on SBM Offshore’s Fast4Ward programme, using the company’s tenth new-build multi-purpose floater hull. SBM said the development would require the highest gas-handling capacity ever deployed on an FPSO.
The vessel will be designed to process 1.2 billion standard cubic feet of gas per day and produce up to 250,000 barrels of condensate per day, with storage capacity of around 2 million barrels. It will be spread-moored in water about 1,750 metres deep, roughly 200 kilometres offshore Guyana.
It is SBM Offshore’s sixth FPSO project with ExxonMobil Guyana, following Liza Destiny, Liza Unity, Prosperity, ONE GUYANA and Jaguar. SBM said it intends to source some fabrication locally, but did not name any Guyanese firms or say how much of the work it plans to place in Guyana.
Longtail is the eighth development in the Stabroek Block and the first built around non-associated gas and condensate, targeting reservoirs in the southeastern portion of the block, near the Suriname maritime border. The development is expected to include about 45 subsea production and injection wells across nine reservoirs — 27 production wells and 18 gas injection wells, according to the government’s development plan.
ExxonMobil announced the final investment decision on November 12, with a planned investment of $12.5 billion and start-up targeted for 2030. Guyana’s Ministry of Natural Resources has said the project is expected to produce roughly 776 million barrels of condensate over a 30-year operating life.
ExxonMobil Guyana operates the Stabroek Block with a 45% interest, alongside Hess Guyana Exploration, part of Chevron, with 30%, and CNOOC Petroleum Guyana with 25%.