ExxonMobil says copying Longtail could save $2 billion on Haimara gas project
Summary: ExxonMobil says it can save $2 billion or more on its next big Guyana gas project by barely designing it at all — just reuse Longtail’s plans. Haimara, the second phase of the offshore gas build-out, would use essentially the same FPSO design, the same suppliers and the same construction deals.
The quick version:
- What happened: ExxonMobil Guyana president Alistair Routledge told reporters Nov 24 that Haimara could save US$2 billion or more by reusing Longtail’s engineering designs, suppliers and construction arrangements — “design one, build two.”
- The trick: Haimara would use essentially the same FPSO design as Longtail — same drawings, same materials, same supply chain, same fabrication yards.
- The catch: The savings only work if Haimara’s schedule stays lined up with Longtail’s. Slip the schedule, lose the shared deals.
- The bonus: The same coordination could save up to US$200 million on Longtail itself, even though that project is already underway.
- Where it stands: Haimara is not yet sanctioned and has no FPSO contractor. ExxonMobil is targeting a final investment decision in 2027. It would be the ninth Stabroek development.
- What’s next: Environmental studies are nearly done, with public consultations expected early next year.
The story:
ExxonMobil has a money-saving idea for Guyana’s next gas project: don’t design a new one. Just build Longtail twice.
Company president Alistair Routledge told reporters Tuesday that Haimara — the second phase of the offshore gas development in the southeastern Stabroek Block — could save $2 billion or more by reusing Longtail’s engineering designs, suppliers and construction arrangements.
“If we can reuse the same drawings, the same materials purchases, the same supply chain, go through the same fabrication yards, then we can see a path with an optimized project management team to be able to squeeze significant savings out of the project execution,” he said.
The plan is “design one, build two.” Haimara would use essentially the same FPSO design as Longtail — the floating production vessel that will process 1.2 billion cubic feet of gas a day plus up to 250,000 barrels of condensate.
There’s a catch, and Routledge said it plainly: the savings depend on keeping Haimara’s schedule aligned with Longtail’s. The shared suppliers, equipment and construction deals only work if the two projects move together. That’s why ExxonMobil is targeting a final investment decision for Haimara in 2027.
The same teamwork could pay off twice — coordination between the projects could save up to $200 million on Longtail itself, even though that project is already in its early stages.
Longtail, sanctioned earlier this month at $12.5 billion, is the first Stabroek development built for gas and condensate rather than oil, with production targeted for 2030. SBM Offshore is building and installing its FPSO. Haimara would follow as the ninth Stabroek development — but it isn’t sanctioned yet, and no FPSO contractor has been picked.
Environmental studies for Haimara are nearing completion, with public consultations on the findings expected early next year. Together, Routledge said, Longtail and Haimara are the first big steps in a multi-decade gas strategy meant to power Guyana’s industries and homes for years to come.